Ascot Provides an Update on Mine Development & Restart of Operations

In This Article:

Ascot Resources Ltd.
Ascot Resources Ltd.

VANCOUVER, British Columbia, April 15, 2025 (GLOBE NEWSWIRE) -- Ascot Resources Ltd. (TSX: AOT; OTCQX: AOTVF) (“Ascot” or the “Company”) is pleased to provide an update of its activities related to the restart of operations at the Premier Gold Project ("PGP" or the "Project"), located on Nisga'a Nation Treaty Lands in the prolific Golden Triangle of northwestern British Columbia.

As announced on April 10th, 2025, the Company closed the second and final tranche of its private placement financing, raising a total of $61.1 million in gross proceeds (the “Financing”).

MINE AND INFRASTRUCTURE DEVELOPMENT

Power availability increased to allow expanded equipment operations:

  • With the closing of the Financing, Ascot is addressing the critical issue of expanding power capacity by ordering a 4160v transformer for the Premier Northern Lights (“PNL”) workings and additional camp space.

  • The new transformer is expected to allow several pieces of equipment to operate simultaneously, improving the current situation where power capacity limits the number of pieces of equipment operated at a time.

  • The transformer is on site and installation is underway with the additional power expected to be available within several days.

Camp capacity increased to support restart:

  • In addition, Ascot is adding additional camp space following the closing of the Financing.

  • Ascot has ordered a 76-bed expansion for the camp (a 100% increase) to accommodate additional personnel as the Company proceeds toward a restart of operations.

  • The first 38 beds have already been installed, with the remainder expected to be installed in June 2025.

With the additional power capacity and camp space, Ascot anticipates that its mining contractor, Procon Mining and Tunnelling, will be positioned to increase productive operation.

Mine development advancing:

  • Through April 13th, 2025, Procon has completed more than 800 metres of mine development since remobilization in late December 2024.

  • Mining areas are currently being developed on the 310 and 330 and levels of the high grade Prew zone in the PNL workings.

  • In conjunction with the above, the Company has commenced the re-opening of the Big Missouri workings, where work was paused when PGP was placed on care and maintenance last fall. The road to Big Missouri has been plowed and infrastructure is being reinstalled to begin pumping the accumulated water in the heading. Procon is in the process of remobilizing equipment for Big Missouri with development expected to start there in May 2025.

  • With contributions from both PNL and Big Missouri, Ascot targets the stockpiling of 40,000 tonnes of material for processing prior to mill startup.