Maritime Announces the Start of Mineral Processing Operations at Pine Cove

In This Article:

Toronto, Ontario--(Newsfile Corp. - February 27, 2025) - Maritime Resources Corp. (TSXV: MAE) (OTC Pink: MRTMF) ("Maritime" or the "Company") is pleased to announce it has commenced mineral processing operations at the Company's Pine Cove Mill. Pine Cove is part of the larger Point Rousse Gold Project, located in the Baie Verte mining district of Newfoundland and Labrador, near the towns of Ming's Bight and Baie Verte.

Highlights:

  • Processing of crushed feed from mineralized stockpiles has commenced at the Pine Cove Mill

  • Process plant repairs and upgrades are largely complete

  • Operations, maintenance and supervisory positions recruited 100% from local communities

  • To date over 50,000 tonnes of mineralized stockpile material crushed and ready to be processed (Figure 2)

Garett Macdonald, President and CEO comments, "We are very pleased to announce the commencement of mineral processing operations at the Pine Cove Mill, currently the only operating gold processing facility in the Province. The first stage of upgrades to the plant's gold circuit have been completed, the high voltage connection has been energized and processing of crushed feed from the existing mineralized stockpiles has commenced. Returning the plant to operations after acquiring the asset in 2023 is a major milestone for the Company and the Region, setting the stage for a low capital cost startup of our Hammerdown Gold Project later this year."

Pine Cove Mill

After a two-year period of care and maintenance the Pine Cove process plant has been returned to operations and processing of stockpiled material has commenced. In the past four months Maritime has assembled a workforce of 37 personnel at Pine Cove, including mill supervision, operators and maintenance personnel, recruited 100% from the local communities in the district. The team completed the necessary repairs and upgrades to the plant electrical and mechanical systems by performing the work, in large part, with our in-house team resulting in significant cost savings. The major work items included a complete refurbishment of the plant's electrical systems, both drum filters have been refitted, both ball and regrind mills have been re-lined, mechanical repairs to leach tanks and the thickener completed, a new concrete base for a leach tank, installing a new ball mill lube system and enhancements to the PLC system. The 4,160 kV high voltage transformer has been energized to the 600 kilowatt ball mill (Figure 1).

The Pine Cove Mill circuit is rated for 1,300 tonnes per day (475,000 tonnes per year) and is configured as a crush, primary grind, flotation, concentrate regrind followed by leaching to gold doré through a Merrill Crowe system. An existing Falcon gravity concentrator will be installed once the mill is running in preparation for feed from Hammerdown or other sources. Tailings is stored in the former Pine Cove open pit mine, now a permitted in-pit storage facility with over 3.5 million cubic metres of available storage volume.