Moneta Continues to Report Significant Infill Results at the Tower Gold Project, Including 42.55 m @ 4.03 g/t Gold from Westaway

Toronto, Ontario--(Newsfile Corp. - June 20, 2023) - Moneta Gold Inc. (TSX: ME) (OTCQX: MEAUF) (FSE: MOPA) ("Moneta" or the "Company") is pleased to announce assay results from fifty-four (54) resource infill and step-out drill holes on the Westaway deposit at the Tower Gold project (the "Project"), located in the Timmins Gold Camp, Ontario. The drilling was conducted as part of an initial 76,000 metres ("m") drilling program, completed in 2022, and an additional 60,000 m drilling program that is currently underway. Both drilling programs are designed for resource upgrade and infill of the 4.5 million ("M") ounces ("oz") indicated gold ("Au") and 8.3 Moz inferred Au mineral resource estimate (see September 07, 2022 press release).

Drilling Highlights:

  • MGH23-388 intersected 42.55 m @ 4.03 grams per tonne "g/t" Au, including 19.25 m @ 6.74 g/t Au, including 4.00 m @ 12.89 g/t Au

  • MGH22-336 intersected 29.83 m @ 2.62 g/t Au, including 19.83 m @ 3.73 g/t Au

  • MGH23-359 intersected 29.00 m @ 2.47 g/t Au, including 9.00 m @ 5.67 g/t Au, including 3.00 m @ 11.31 g/t Au

  • MGH23-357 intersected 27.00 m @ 1.94 g/t Au, including 10.00 m @ 2.50 g/t Au, and 5.00 m @ 5.09 g/t Au

  • MGH23-352 intersected 26.50 m @ 1.69 g/t Au, including 5.00 m @ 4.00 g/t Au, and 3.00 m @ 2.70 g/t Au

  • MGH23-385 intersected 23.80 m @ 1.86 g/t Au, including 1.00 m @ 7.28 g/t Au, and 6.40 m @ 3.92 g/t Au, including 3.00 m @ 6.44 g/t Au

  • MGH23-350 intersected 4.45 m @ 9.56 g/t Au

  • MGH23-393 intersected 10.65 m @ 3.64 g/t Au, including 1.00 m @ 18.65 g/t Au

  • MGH23-350 intersected 14.00 m @ 2.38 g/t Au, including 8.45 m @ 3.52 g/t Au

Gary O'Connor, Moneta's President and Chief Executive Officer, commented, "These latest assay results from infill and step-out drilling continue to confirm the continuity and extensions of gold mineralization at Westaway, on the Tower Gold project. The drilling has been focussed on the open pit portions of the mineral resources as defined in the current Preliminary Economic Assessment ("PEA") study during the first 11 years of production. Continuity of good gold mineralization have also been intersected within the underground and outside the initial open pit areas. As we continue to grow, de-risk, and advance the Project, we look forward to completing the current resource infill and upgrade drill program in preparation of a mineral resource estimate update for planned optimization studies."

A total of 10,888.0 m of drilling was completed in fifty-four (54) drill holes. Drilling is being conducted on 50 m centres as step-outs and infill of previous drill holes. All assays are now released from 2022 drilling. Additional assays from 2023 drilling are pending and will be released upon receipt of assays.